ARAMCO Safaniya Clean Fuels

Engineering & Marketing International
Technology

Aveva

Industry

Oil and Gas

Client

ARAMCO

Country

KSA

Goals

Integrate PCS system data smoothly into ARAMCO’s existing PI infrastructure

Ensure high system reliability and continuous PI data availability

Provide effective monitoring and reporting through rich visual and tabular tools

Challenges

Managing and interfacing up to 50,000 PI tags from Honeywell OPC servers

Configuring multiple OPC DA interfaces securely and reliably

Delivered numerous custom graphics and reports on a tight schedule

Solutions

Installed and configured PI OPC DA Interfaces at dedicated PI Buffer nodes

Connected and validated all 50,000 data tags for accurate real-time data flow

Developed and deployed over 1,200 PI ProcessBook graphics for operations

Created 55 Excel Datalink reports for routine monitoring and analysis

Results

Achieved seamless integration of PCS data into ARAMCO’s PI System

Delivered a scalable, high-performance PI system with rich visualization

Ensured reliable operations with continuous real-time and historical access

Enhanced plant transparency and improved operational decision-making

ARAMCO SAFANIYAH Clean Fuels
DAHS & PI System Integration

In 2020, EMI was commissioned by Honeywell KSA to implement the Data Acquisition and Handling System (DAHS) for the ARAMCO SAFANIYAH Clean Fuels Project. This high-profile downstream initiative focused on establishing a seamless and highly reliable data integration between the newly installed Process Control System (PCS) and ARAMCO’s local PI infrastructure. EMI’s role was crucial in ensuring that large volumes of process data from Honeywell OPC servers could be securely and efficiently channeled into the PI System, supporting operational continuity and real-time performance monitoring.

To meet these objectives, EMI deployed a robust architecture including multiple PI Buffer nodes (PIBs) to act as reliable data collection points. The project involved configuring and validating an extensive number of tags — up to 50,000 — ensuring data integrity and availability throughout the facility. In addition to the back-end data integration, EMI developed an extensive library of PI ProcessBook displays and customized Excel Datalink reports, enabling the plant operations team to access vital performance metrics via intuitive graphical and tabular formats.

One of the project’s key success factors was balancing the delivery of complex data interfaces and high tag volumes with strict time constraints. EMI carefully managed secure OPC DA interface setups to align with best practices and ARAMCO’s cybersecurity requirements. The integration effort resulted in a scalable, high-performance PI environment capable of supporting both current and future operational needs, ultimately enhancing decision-making and transparency at the Safaniyah Clean Fuels plant.