Technology
Aveva
Industry
Oil and Gas
Client
ARAMCO
Country
KSA
Goals
Upgrade legacy PI Server to PI 2015
Implement High Availability (HA) system
Configure redundant OPC interfaces for four GOSPs
Develop 160+ customized ProcessBook displays
Challenges
Live migration with minimal downtime
Ensuring failover and redundancy
Rapid development of numerous displays
Remote site coordination
Solutions
Dedicated PI engineers collaborating with local engineers onsite
Configured redundant OPC interfaces
Established HA PI Server Collective
Developed tailored ProcessBook displays
Results
Successful transition to modern, reliable PI System
Real-time, clear operator visualizations
Increased data integrity and system uptime
Strong collaboration ensured project success
ARAMCO Shaybah PI System UpgradeThe Shaybah oil field, located deep within the Rub' al Khali desert, is one of Saudi Aramco’s most remote yet strategically vital upstream production sites. In 2015, EMI was hired to undertake a comprehensive upgrade of the PI System infrastructure that supports four Gas-Oil Separation Plants (GOSPs) at Shaybah. This upgrade was critical to ensure reliable, continuous data acquisition, storage, and visualization, which are fundamental to the safe and efficient operation of these complex facilities. The existing PI System was aging, and there was an urgent need to migrate to a more modern and robust platform to handle increasing data volumes and provide enhanced system reliability. |
![]() |
EMI’s role included not only the migration and upgrade of the PI Servers but also the implementation of a high-availability (HA) system architecture to eliminate single points of failure. This HA setup was designed to maintain system uptime even during hardware failures or maintenance, which is vital for uninterrupted plant monitoring and control. One of the major aspects of the project was configuring redundant OPC interfaces to connect with AIM OPC servers from each of the four GOSPs. This redundancy ensured that data would continue to flow smoothly even if one interface failed.
|
|
Ultimately, this upgrade resulted in a resilient, modern PI infrastructure that improved data integrity, operational transparency, and system reliability—empowering operators with the tools needed for better decision-making and reducing operational risks. The success of this project has set a foundation for ongoing digital transformation and continuous improvement at the Shaybah facility.